Development Control Division Services f

Type of Services Procedure Time Frame Contact Person
Obtain Building Permit
  1. Applicant submits dully filled form D along with 2 sets of building drawing as per the checklists
  2. Building drawing scrutiny
    1. Architectural
    2. Structural
    3. Electrical
    4. Water supply and sewerage
    5. Bhutan Power Clearance
  3. Signing of construction agreement, issue bills and receipts for scrutiny fee and final issuance of approval

Note: Since PCC has a system of maintaining diary number and receipt date punched on each applicants drawings, the timeline shall remain applicable in case of single building drawing scrutiny. However if one applicant submits more than one building at a time on a single day, separate diary number shall be issued for each building drawing and accordingly approval timeline shall be intimated/informed.

15 days per drawing
  1. Mr.Tshewang Jaipo, Architect for Architectural drawing
  2. Mrs. Yeshei Choden( Structural Engineers) for structural drawing
  3. Mr.Nakchung, Electrical Engineer for electrical drawing
  4. Mr.Namgay Phuntsho, 05-252887 for water supply and sewerage drawing Sonam Jamtsho, 05-253306

 

Permit/Approval for Major renovations/constructions(Roofing, Internal modifications, retaining wall, fencing, gate, temporary shed etc)
  1. Submits the application along with proposed darwings
  2. Site verification and inspection
  3. 3.Drawing scrutiny for approval
7 days Structural Engineer, DCD
Permit/Approval for Minor renovations/constructions(Whitewashing, painting, changing door-window shutters, ceilings, plinth protection, drainage etc)
  1. Submits the application
  2. Site verification and inspection
5 days Structural Engineer, DCD
Monitoring of building construction at various stages
  1. Verify building layout plan before starting the construction works
  2. Check for reinforcement and casting on footings and columns
  3. Check and verify for reinforcement and casting on plinth beams as per approved drawings
  4. Check and verify slab casting for each floors
  5. Verify roof projection and CGI sheetings
Routine Inspection Building Inspectors, DCD
Obtaining Occupancy Certificate (OC)
    1. Submits dully filled application form K along with completion certificate form J
    2. PCC and owner jointly verifies the completed building for issuance of OC
7 days  Building Inspector, DCD